Instagram YouTube

News

May 6, 2022
April 2022 Construction Update

TABLE OF CONTENTS

  1. Neighbor Relations
  2. Project Summary

 

I.   NEIGHBOR RELATIONS

No neighbor issues to report.

 

II.    PROJECT SUMMARY

 Current Progress

 Maine East: The A Building lower level Technology offices are currently being painted. Lighting is being installed and space wrapping up in the near future. Scaffolding has been set adjacent to A Building. Exterior openings are complete to create access points into the attic space. MEP installation in the attic continues.

Maine South: Punch list activities continue throughout the school. Spring Break allowed for completion of several items as well as the use of Friday 4/15.

Maine West: B Wing is currently occupied with punch list activities occurring. C Wing Gym work continuing with drywall and MEP installation. Painting and ceilings to follow over the next few weeks.

Construction Budget

Budget and Phasing provided during the January B&G meeting.

Bid Period No. 4

PCC presented BP4 results in March. Prime Trade Agreements and procurement of this new material is currently underway.