TABLE OF CONTENTS
- Neighbor Relations
- Project Summary
I. NEIGHBOR RELATIONS
No neighbor issues to report.
II. PROJECT SUMMARY
Current Progress
Maine East: The A Building lower level Technology offices are currently being painted. Lighting is being installed and space wrapping up in the near future. Scaffolding has been set adjacent to A Building. Exterior openings are complete to create access points into the attic space. MEP installation in the attic continues.
Maine South: Punch list activities continue throughout the school. Spring Break allowed for completion of several items as well as the use of Friday 4/15.
Maine West: B Wing is currently occupied with punch list activities occurring. C Wing Gym work continuing with drywall and MEP installation. Painting and ceilings to follow over the next few weeks.
Construction Budget
Budget and Phasing provided during the January B&G meeting.
Bid Period No. 4
PCC presented BP4 results in March. Prime Trade Agreements and procurement of this new material is currently underway.